โšก Brain Dump Reference Card

Everything to write on scratch paper in the first 5 minutes before starting questions
Exam Day ยท Print This ยท Practice Writing in Under 5 Minutes
โฑ Target: Under 5 Minutes

Write this on your scratch paper before touching Question 1. Practice daily during your last 2 weeks of prep.

๐Ÿ“Š EVM Formulas

MetricFormulaMeaning
SVEV โˆ’ PVโˆ’ = behind sched
CVEV โˆ’ ACโˆ’ = over budget
SPIEV / PV<1 = behind sched
CPIEV / AC<1 = over budget
EAC (typ)BAC / CPIDefault on exam
EAC (atyp)AC + (BACโˆ’EV)One-time variance
EAC (both)AC + (BACโˆ’EV)/(CPIร—SPI)Both factors
ETCEAC โˆ’ ACCost to finish
VACBAC โˆ’ EACโˆ’ = over at end
TCPI(BACโˆ’EV) / (BACโˆ’AC)>1 = must improve
EV is always first in variances and numerator in indices. P = schedule, C = cost.

๐Ÿ“ Other Key Formulas

FormulaEquation
Comm Channelsn(nโˆ’1) / 2
PERT(O + 4M + P) / 6
Std Dev (ฯƒ)(P โˆ’ O) / 6
PTA (FPIF)((CPโˆ’TP)/BSR) + TC
PERT: O=optimistic, M=most likely, P=pessimistic. PTA only for FPIF contracts.

๐Ÿค Conflict Resolution (PMI Order)

  • 1. Collaborate/Problem Solve โ€” Win-win โญ PMI's #1
  • 2. Compromise โ€” Each gives up something
  • 3. Smooth/Accommodate โ€” Emphasize agreement
  • 4. Force/Direct โ€” Emergency only
  • 5. Withdraw/Avoid โ€” Temporary retreat

โš ๏ธ Risk Response Strategies

Threats (โˆ’)Opportunities (+)
AvoidExploit
TransferShare
MitigateEnhance
Accept (both) ยท Escalate (both)

๐Ÿ‘ฅ Tuckman's Stages

  • Forming โ†’ Polite, uncertain (PM: Direct)
  • Storming โ†’ Conflict, power struggles (PM: Coach)
  • Norming โ†’ Trust, cohesion (PM: Support)
  • Performing โ†’ High productivity (PM: Delegate)
  • Adjourning โ†’ Closure (PM: Celebrate)

๐Ÿ“ Contract Types (Buyer Risk โ†’ Seller Risk)

  • CPPC โ€” Cost + % of cost (worst for buyer)
  • CPFF โ€” Cost + fixed fee
  • CPIF โ€” Cost + incentive fee
  • T&M โ€” Time & materials (shared)
  • FPIF โ€” Fixed price + incentive (PTA applies)
  • FFP โ€” Firm fixed price (worst for seller)

๐Ÿ“‹ Change Control Process

  • 1. Change identified
  • 2. Assess impact (scope, schedule, cost, risk)
  • 3. Submit change request
  • 4. CCB reviews (approve/reject/defer)
  • 5. Update plans & baselines if approved
  • 6. Communicate decision
NEVER make the change immediately. ALWAYS assess first.

๐Ÿง  PMI Mindset Quick Rules

  • Servant leadership > authority
  • Assess before acting (always)
  • Follow the process (always)
  • Never gold plate
  • Ethics first (honesty, responsibility, respect, fairness)
  • Engage stakeholders early & continuously
  • Charter = PM's authority
  • Facilitate > Direct

๐Ÿงญ 12 PMBOK 7 Principles

People (4)Approach (4)Outcome (4)
1. Stewardship5. Systems Thinking4. Value
2. Team7. Tailoring8. Quality
3. Stakeholders9. Complexity10. Risk
6. Leadership11. Adaptability12. Change

โฑ Exam Timing Reference

DetailValueDetailValue
Questions180 (175 scored)Time per Q~76 seconds
Total time230 minutesBreak 1After Q60 (10 min)
DomainsPeople 42% ยท Process 50% ยท Biz 8%Break 2After Q120 (10 min)
Read the LAST sentence first. Eliminate 2 wrong answers. Flag & move on if > 2 min. Take BOTH breaks. Don't change answers unless certain you misread.
๐ŸŽฏ Practice Plan

Last 2 weeks: Practice writing this entire brain dump from memory every day. Time yourself โ€” target under 5 minutes.

Exam day: Write it on scratch paper during the tutorial/survey time before Q1. This frees your working memory for scenario analysis.

Print this page and keep it next to your study materials for daily practice.