โฑ Target: Under 5 Minutes
Write this on your scratch paper before touching Question 1. Practice daily during your last 2 weeks of prep.
๐ EVM Formulas
| Metric | Formula | Meaning |
| SV | EV โ PV | โ = behind sched |
| CV | EV โ AC | โ = over budget |
| SPI | EV / PV | <1 = behind sched |
| CPI | EV / AC | <1 = over budget |
| EAC (typ) | BAC / CPI | Default on exam |
| EAC (atyp) | AC + (BACโEV) | One-time variance |
| EAC (both) | AC + (BACโEV)/(CPIรSPI) | Both factors |
| ETC | EAC โ AC | Cost to finish |
| VAC | BAC โ EAC | โ = over at end |
| TCPI | (BACโEV) / (BACโAC) | >1 = must improve |
EV is always first in variances and numerator in indices. P = schedule, C = cost.
๐ Other Key Formulas
| Formula | Equation |
| Comm Channels | n(nโ1) / 2 |
| PERT | (O + 4M + P) / 6 |
| Std Dev (ฯ) | (P โ O) / 6 |
| PTA (FPIF) | ((CPโTP)/BSR) + TC |
PERT: O=optimistic, M=most likely, P=pessimistic. PTA only for FPIF contracts.
๐ค Conflict Resolution (PMI Order)
- 1. Collaborate/Problem Solve โ Win-win โญ PMI's #1
- 2. Compromise โ Each gives up something
- 3. Smooth/Accommodate โ Emphasize agreement
- 4. Force/Direct โ Emergency only
- 5. Withdraw/Avoid โ Temporary retreat
โ ๏ธ Risk Response Strategies
| Threats (โ) | Opportunities (+) |
| Avoid | Exploit |
| Transfer | Share |
| Mitigate | Enhance |
| Accept (both) ยท Escalate (both) |
๐ฅ Tuckman's Stages
- Forming โ Polite, uncertain (PM: Direct)
- Storming โ Conflict, power struggles (PM: Coach)
- Norming โ Trust, cohesion (PM: Support)
- Performing โ High productivity (PM: Delegate)
- Adjourning โ Closure (PM: Celebrate)
๐ Contract Types (Buyer Risk โ Seller Risk)
- CPPC โ Cost + % of cost (worst for buyer)
- CPFF โ Cost + fixed fee
- CPIF โ Cost + incentive fee
- T&M โ Time & materials (shared)
- FPIF โ Fixed price + incentive (PTA applies)
- FFP โ Firm fixed price (worst for seller)
๐ Change Control Process
- 1. Change identified
- 2. Assess impact (scope, schedule, cost, risk)
- 3. Submit change request
- 4. CCB reviews (approve/reject/defer)
- 5. Update plans & baselines if approved
- 6. Communicate decision
NEVER make the change immediately. ALWAYS assess first.
๐ง PMI Mindset Quick Rules
- Servant leadership > authority
- Assess before acting (always)
- Follow the process (always)
- Never gold plate
- Ethics first (honesty, responsibility, respect, fairness)
- Engage stakeholders early & continuously
- Charter = PM's authority
- Facilitate > Direct
๐งญ 12 PMBOK 7 Principles
| People (4) | Approach (4) | Outcome (4) |
| 1. Stewardship | 5. Systems Thinking | 4. Value |
| 2. Team | 7. Tailoring | 8. Quality |
| 3. Stakeholders | 9. Complexity | 10. Risk |
| 6. Leadership | 11. Adaptability | 12. Change |
โฑ Exam Timing Reference
| Detail | Value | Detail | Value |
| Questions | 180 (175 scored) | Time per Q | ~76 seconds |
| Total time | 230 minutes | Break 1 | After Q60 (10 min) |
| Domains | People 42% ยท Process 50% ยท Biz 8% | Break 2 | After Q120 (10 min) |
Read the LAST sentence first. Eliminate 2 wrong answers. Flag & move on if > 2 min. Take BOTH breaks. Don't change answers unless certain you misread.
๐ฏ Practice Plan
Last 2 weeks: Practice writing this entire brain dump from memory every day. Time yourself โ target under 5 minutes.
Exam day: Write it on scratch paper during the tutorial/survey time before Q1. This frees your working memory for scenario analysis.
Print this page and keep it next to your study materials for daily practice.